LIST OF COMPLETED PROJECTS

S/N

Name of Project

Client / Location

Completion Date

Scope of Work

1

DMCI Power Corporation

Sta. Isabel, Calapan City, Mindoro Oriental

Aug.2014 Feb. 2015

Electro Mechanical Installation for 4 x 3.7MW 9L32 Wartsila Diesel Engine


2

Peak Power Soccsargen (SOCOTECO II)

Brgy. Apopong, General Santos City

10 months (Dec. 2013 – Oct. 2014)

Engineering & Construction of SOCOTECO II 20.9MW Power Plant Project (3 x Wartsila 16V32 Engine Set)

3

Peak Power San Francisco (ASELCO)

Brgy. San Isidro, San Francisco Agusan del Sur

8 months (Jan. 2014 – Aug. 2014)

Engineering & Construction of ASELCO 5.2MW Power Plant Project (1 x Wartsila 12V32 Engine Set)

4

King Energy Gen. Inc. -Surigao Sur Power Plant,

Tandag City, Surigao del Sur

5 months (Dec. 2013 – May. 2014)

Mechanical Installation of 7.8MW (1xW18V32 Engine Set) Surigao Sur Power Plant

5

Iligan – Mapalad Electric Corp

Iligan City

3months (2012 – 2013)

Civil works & tanks fabrication for tank farm.

6

Iligan – Mapalad Electric Corp.

Iligan City

6 months (2013)

Electro – Mechanical Installation of 2 x 7.5MW Sulzer Gensets.

7

SI Power Corporation

Lazi and WSiquijor

8 months (2013)

4 x 1.616MW Packaged Power Station

8

Mindanao Energy System (MINERGY)

Brgy. Tablon, Cagayan de Oro City

45 Days

Dismantling of Existing HFO Pipe Line

9

JG Summit Petrochemical Corporation

Brgy. Simlong, Batangas

13-May

Mechanical installation of five (5) 5.0MW Wartsila Engine

10

Calapan Power Generating Corp.

Calapan, Oriental Mindoro

13-May

Engine & Generator Alignment (including foundation grouting & piping works).

11

Minergy-CEPALCO

Tablon, Cagayan de Oro

12-Oct

Repair / Replacement of Exhaust Gas Silencers and Chimneys for 3 x 5.0MW Sulzers Gensets.

12

Minergy-CEPALCO

Tablon, Cagayan de Oro

11-Feb

Civil / Mechanical / Electrical works for 2 x 13.7MW Wartsila Gensets at Tablon CDO.

13

Minergy-CEPALCO

Tablon, Cagayan de Oro

10-Jun

Dismantling / Shipping from Taiwan 2 x 13.7MW Wartsila Gensets .

14

Greenstone Resources Corp.

Siana, Surigao

11-Mar

Installation of 3×2.0MW Caterpillar Genset model 3608 at Siana, Surigao Mine Site

15

Greenstone Resources Corp.

Siana, Surigao

11-Jan

Dismantling & Refurbishment of 3 x 2.0MW Caterpillar Genset Model 3608 at San Pedro, Laguna

16

Semirara Mining Corp.

Semirara Island, Antique

11-May

Installation of 1 x 5.7MW 16V32 Wartsila at Semirara Island Mine site.

17

Semirara Mining Corp.

Semirara Island, Antique


Dismantling of 1 x 5.7MW 16V32 Wartsila at Goodyear Compound, Las Piñas City

18

Masbate Gold Mining Power Station

Filminera Resources Corp. / Leighton Contractor’s Asia Ltd. – Aroroy,

December 2008 – May 2009

Electro-Mechanical Design, Engineering & Installation of a 30 Megawatt Diesel Power Plant, Three (3) units Wartsila Vasa 18V32 & Two (2) units Wartsila Vasa 16V32 Gensets

19

Ramirez Construction


8-Sep

Structural fabrication and erection of Manila Bulletin Warehouse.

20

Nestle

Cabuyao, Laguna

Year 2008

Exhaust Gas Boiler Installation

21

Nestle

Cagayan De Oro

Year 2007

7.8 MW Wartzila Mechanical Auxilliary Installation & Piping Expansion Works

22

Monde Energy Cogeneration Inc.

Sta. Rosa, Laguna

Year 2006

Construction & Commissioning of Boiler Flue Gas Scrubber & Economizer

23

GNF Phils., Inc.

GNF Philippines, Inc. – Sta. Rosa, Laguna

Year 2005

Power plant phase 1 exhaust system modification – 4 units

24

BIPCOR

Salcon,

Year 2005

25

Prince Paper Corp.

Prince Paper Corp. – Panipuan, , Pampanga

Year 2005

1 x 5.0MW Mitsubishi Genset, chimney fabrication

26

Container Corp.

Container Corp.

Year 2004

1 x 2.5 MW Daihatsu, Civil & Electromechanical Works

27

Lazard Power Corp.

TNPMC

Electrical Sub-station, Civil & Structural Works

28

Lazard Power Corp.

TNPMC

Year 2003

12.0MW Power Plant Electromechanical works

29

Dragon Textile

Dragon Textile – Lalaan, Silang Cavite


Valve Cage repair

30

Calibu Power Plant

Calibu Power Plant


Modification/transfer/structural Support for Air Filters of 5 x 6.3 MW Gensets

31

Calibu Power Plant

Calibu Power Plant

Year 2002

Design & Fabrication / Installation of 750mm dia. hydraulic operated butterfly valve for boiler by-pass Ducts

32

Calibu Power Plant

Angeles Power, Inc. – Pampanga


Fabrication & Erection of 40 meters high support structure for 5 x 900mm dia. Chimney

33

Calibu Power Station

Angeles Power, Inc. – Pampanga


Installation of Five (5) 6.3Mw 12ZA40 Sulzer gensets

34

Air Liquid

Air Liquid Philippines, Inc. –

Year 2001

Complete overhualing of One (1) unit 5,000KW 12Kv Major MK3 Mirlees Blackstone

35

Benguet Power Station

Philex Mining’s Benguet – Padcal, Tuba, Benguet

Year 1997

Rehabilitation, Overhaul & Commissioning of two (2) 8.0MW Niigata Pielstick 18PC 2.5V & Four (4) 5.0MW Mirrlees Blackstone KV 16 Major

36

Sibutad Power Station

Philex Gold’s Sibutad – Sibutad, Zamboanga del Norte

Year 1996

Installation of One (1) 1.5MW 6L31EZ & Four (4) KM transmission line & Two (2) KM pipelines